Water Treatment Plant Project
Construction of the new St. Marys Water Treatment Plant began on August 6, 2018, with the construction of a parking pad. The groundbreaking ceremony was held on Friday, August 10th and was officiated by St. Marys Mayor, Patrick McGowan. Also in attendance was Ohio's 82nd District Representative, Craig Riedel, along with representatives from Peterson Construction Company, Jones and Henry Engineers, and various City officials.
The new plant will be located at the intersection of SR66a and Koop Road and is expected to be completed in about twenty months. The cost of the plant is approximately 18 million dollars. View the Water Treatment Plant Elevations Blueprint (PDF). View the Water Treatment Plant Project photo gallery.
September 20, 2018
The first major concrete pour began today with the construction of a lower level holding tank base. The eighteen-inch thick base took approximately 89 yards of a specialized concrete mix to complete. Attached below are several pictures taken during the work.
November and December, 2018
The outer walls of the plant processing building are starting to take shape. The final floor height of the main level is up to grade and will be ready to pour after electrical conduits are installed. Below are some pictures of the progress.
January and February, 2019
As expected, the weather during the last several months has been less than cooperative. Rain, snow, and bitter temperatures have hampered the process of pouring concrete. In spite of the weather, work continues on the main process floor with the installation of piping, etc. A break in the weather on February 22 allowed for more concrete to be added. Several aerial photos of the progress can be seen below.
July and August, 2019
The main process area of the new plant is beginning to take shape and construction began on the two above-ground clear water storage tanks. The steel building that will complete the top of the plant is delayed until October, but should not affect the building schedule. Construction of the administration portion of the plant got underway in July. Several photos of the construction can be seen below.
November, 2019
The steel structure that tops the building was delivered near the end of October and construction started immediately. By early November, the structure is starting to take shape.